A Project Profile Sheet will be prepared for each High Priority Project. The project sheet should include the project outline with project rationale and justification, along with conceptual drawings (if necessary) to facilitate the understanding of readers. The next stage of project implementation, i.e., DPR 1, should commence from this project sheet. The project sheet should include the following items:

  • Project Code;
  • Project Name;
  • Categories;
  • Location;
  • Rationale and Justification;
  • Objectives;
  • Status;
  • Anticipated Timeframe;
  • Project Description ;
  • Social and Environmental Impacts;
  • Implementation Arrangements;
  • Cost;
  • Implementation Schedule; and
  • Conceptual Site Location and Physical Plan.

Sample project sheets are found in Annex 2.